Chapter 17: Execution Roadmap & Project Plan

The previous 16 chapters cover “what to do.” This one covers “in what order, and when.” Run it as a project: multiple workstreams in parallel, paced by milestone gates.

17.1 Overall timeline (Gantt)

⚠️ Months are illustrative (depends on readiness and SC scheduling). The whole thing commonly takes 12–18 months+; no fast track (see Ch.4).

gantt title DAX setup roadmap (months, illustrative) dateFormat X axisFormat %s section Setup & entity Feasibility + budget :0, 1 Incorporate Sdn Bhd / team :1, 2 Capital in + source proof :1, 3 section Legal & compliance Engage firm/advisors :1, 2 AML + governance build :2, 4 SC pre-engagement :3, 1 section Technology & security Tech choice (buy/build) :2, 2 Build systems+wallet+risk :4, 5 Pen-test + security audit :8, 2 section Application Assemble document pack :4, 2 Submit + queries :6, 8 Conditional approval + meet :13, 2 section Banking & liquidity Engage multiple banks :3, 9 MM / liquidity contracts :10, 4 section Launch Readiness + final checks :14, 2 Go live + ongoing compliance :16, 2

Download the fillable project plan

The Gantt as an editable table — change Start month / Duration, End auto-computes:

Edit “Start month / Duration” (yellow); End = Start + Duration recomputes. Use alongside the Chapter 11 budget model.

17.2 Six parallel workstreams

Split work into 6 parallel tracks, each with an owner, to avoid serial blocking.

flowchart TD PM[Project lead / PMO] --> T1[1) Legal & compliance
firm + compliance officer] PM --> T2[2) Company & capital
CFO] PM --> T3[3) Technology & security
CTO] PM --> T4[4) Banking & payments
finance + compliance] PM --> T5[5) Liquidity & MM
trading/BD] PM --> T6[6) Product & operations
product lead]
WorkstreamKey deliverablesChapters
1) Legal & complianceLicence path, AML system, governance, SC liaison1·4·5·14
2) Company & capitalSdn Bhd, ownership/UBO, RM 5M proof2·3
3) Technology & securityMatching/wallet/risk, pen-test, BCP/DR6·12·15
4) Banking & paymentsOperating account, client trust account7
5) Liquidity & MMMM contracts, aggregation, inventory funds10
6) Product & operationsMVP, support, launch growth12·13

17.3 Milestone gates

Each gate is “don’t proceed until it’s met” — avoid advancing while broken.

flowchart LR G0[G0 Kickoff
funds+commitment] --> G1[G1 Entity ready
company+team+advisors] G1 --> G2[G2 Systems ready
compliance+tech framework] G2 --> G3[G3 Submitted
document pack complete] G3 --> G4[G4 Registered
conditions met] G4 --> G5[G5 Launch-ready
bank+liquidity+security] G5 --> G6[G6 Live
ongoing compliance]
GatePass criteria (summary)
G0 KickoffCash prepared (incl. buffer), core founders in place, feasibility confirmed
G1 Entity readySdn Bhd, local director/secretary, firm + compliance advisor on board
G2 Systems readyAML manual, governance docs, tech architecture, key roles hired
G3 Submitted8-category document pack complete, SC pre-engagement done
G4 RegisteredPassed DD, met conditional-approval prerequisites
G5 Launch-readyBank accounts, liquidity, pen-test, insurance, monitoring all in place
G6 LiveCompliance calendar running, ongoing reporting established

17.4 First-90-days sprint (what you control now)

Approval timing isn’t yours to control, but the quality of the first 90 days decides how fast the rest goes. Spend it on the controllables:

Days 1–30: set direction

  • Feasibility + budget (use the Ch.11 downloadable model)
  • Lock funding source and prepare proof of lawful source (Ch.9)
  • Hire a local firm fluent in CMSA/SC
  • Confirm core founders and initial org

Days 31–60: build the entity

  • Incorporate Sdn Bhd, appoint local director + secretary (Ch.3)
  • Design clear ownership (UBO traceable)
  • Recruit Head of Compliance + AMLCO (key roles first)
  • Tech decision: white-label vs build (Ch.12)

Days 61–90: systems + pre-engagement

  • Draft the AML/CFT manual and governance docs (Ch.5)
  • Settle the tech & security architecture (Ch.6)
  • Pre-engage the SC to calibrate (Ch.4)
  • Start engaging multiple banks (Ch.7)
  • Start engaging MMs / liquidity providers (Ch.10)

💡 After 90 days you should be near gate G2: entity, key people, compliance and tech frameworks in place, ready to assemble materials and file.

17.5 Key dependencies & common bottlenecks

flowchart LR Cap[Capital in] --> Co[Company+capital proof] Co --> App[Submit application] Comp[Compliance system] --> App Tech[Tech+pen-test] --> Ready[Launch-ready] Bank[Banking
common bottleneck] --> Ready Liq[Liquidity
big cost] --> Ready App --> Approve[SC registration] --> Ready
  • Banking: slow and uncertain — most likely to delay you; start earliest and engage multiple banks (Ch.7).
  • SC query rounds: poor materials get bounced repeatedly; better prep is faster (Ch.4).
  • Proof of lawful source: complex UBO slows fit-and-proper (Ch.2).
  • Liquidity: must be arranged before launch, else the book is empty (Ch.10).

17.6 Master checklist: self-assess by chapter

StageSelf-checkChapter
Regulatory awarenessConfirm DAX/RMO path1
EligibilityRM 5M + fit&proper personnel2
Legal entitySdn Bhd + governance3
ApplicationDocument pack + pre-engagement4
ComplianceAML/KYC/STR5
TechnologyWallet/risk/pen-test6
OperationsBank/segregation/listing7
CostsChecklist + timeline8
BudgetResources + 3-year model9
LiquidityMM + inventory funds10
Budget tableDownloadable model11
ProductMVP roadmap12
GrowthGTM + unit economics13
Ongoing complianceReporting calendar14
RiskIncident-response plan15
ReferenceFAQ + glossary16

Summary / action items

  • Assign the six workstreams to owners; set up a PMO/weekly cadence
  • Manage progress with the six gates; don’t advance until met
  • Start the first-90-days sprint now (push all controllables)
  • Start banking and liquidity engagement earliest (the two bottlenecks)
  • Use the 17.6 master checklist to self-assess by chapter on a rolling basis